Local News

Early Rains Slow Wind Farm Work - Road Closures Beginning to Increase

Early week rains washed out some work on the ongoing Alta Farms II Wind Farm for Enel Green Power.

 

According to daily published reports, some work was "weathered out" Monday and Tuesday.

As of Wednesday, 19 of 21 lay down acres were complete and cables for the laydown yard were being delivered Thursday.

 

Also as of Thursday, road closures were starting to add up. Among the closures is Sunset Road from Jenkins Switch Road to Sumpter Road, Thorps Road from Hallsville Road to Mockingbird Road, Flatland Road from Hallsville Road to Mockingbird Road, Sumpter Road from Sunset Road to Tabor Road, Flatland Road from Green Valley Road to Mockingbird Road, Flatland Road from Burr Oak Road to Green Valley Road, Flatland Road from Hallsville Road to Mockingbird Road, Burr Oak Road from Flatland Road to Thorps Road, Flatland Road from Green Valley Road to Mockingbird Road, and Flatland Road from Burr Oak Road to Green Valley Road.

 

All closures were full closures for either culvert work or soil cement stabilization. Local residents residing in these areas have access and have been notified. 

 

Construction signage is going up in the impacted areas. 

Townhall Top of the Hour News

Local Weather - Sponsored By:

CLINTON WEATHER

Local News

DeWittDN on Facebook