A local school is putting the finishing touches on its new and improved sports complex.
Adam Clapp, Superintendent of Monticello Schools, explains that the new restrooms are just about finished, and next, they will finish up the new weight room. He says they are slightly behind schedule, but it should be ready by mid-October.
A new parking lot was put in next to the football field at Monticello High School and Clapp says he didn't expect just how much of an improvement it would be.
Clapp notes they are scheduled to complete the project on October 16th, and as soon as it's ready they will begin using the facilities for fitness classes and sports programs. The improvements will include new bathrooms, a new concessions stand, and a weight room.
As this project comes to a close, Clapp notes they will begin work on the inside of the school building. That will include restrooms and possible additions as the enrollment increases.
If you'd like more information about everything going on at Monticello Schools, visit www.sages.us